Fabrication of HRSG parts including; 18 Boiler Modules, Main and Secondary Steel Structure, Boiler Piping, Pressure Piping (P11, P22, P91), Ducts, Chimney, Installation of the Insulation.
Scope 2:
Erection of all Pressure and Non Pressure Parts, Insulation, Electrification, Instrumentation, Commissioning